Projects

Kenilworth Road Redevelopment

Capital Sky are very proud to have been part of such a rewarding project over the last few months, renovating the Luton Town FC Kenilworth Road ground.

Under time constraints and a very busy site everyone pulled together to make this job a success and reopened the ground in time for the Premier League season for Luton Town.

London City Airport

Runway Demolition & Disposal

Carry out the phased runway demolition and cart away from London City Airport. All works were completed out of hours to ensure no disruption to the airport. Capital Sky used all its own plant and haulage for the works.

All materials removed from the project were transferred to Capital Sky’s yard for processing to ensure all materials were recycled where possible.

Luton Airport DART

Groundworks & RC Frame

Phase 1 – Carry out the groundworks and construction the RC frame for the DART project at Luton Parkway Station. Supply and installation of all reinforcement and concrete under Capital Sky management and engineering. All works were carried out adjacent to a live station environment. We worked closely with our client to ensure no disruption occurred during the project.

Phase 2 – Carry out all groundworks and hard landscaping works at the new Central Station at Luton Airport. This involved break out and removal of existing slabs and hardstanding, laying of new aggregate, drainage, installation of bollards and kerbs all with the confines of a live airport environment.

Thames Road, Barking

Demolition & Disposal

Removal of asbestos and soft strip of existing buildings, full demolition and break out of ground floor slab, removal of foundations up to 1.5m deep, removal of all existing hardstanding within the site boundary and crushing of all demolition arisings and stockpiling on site for future use.

Capital Sky used all its own plant and crusher for the works.

Brandon Road, N7

Kadans Science Partners/CB3 Consulting

We were employed by Kadans Science Partners through CB3 Consulting to carry out the following works as principal contractor at their Brandon Road project in Kings Cross, London;

Carry out asbestos surveys to existing buildings and subsequent asbestos removal works

Installation of perimeter site hoarding to secure the site

Carry out trial pits and surveys to party wall elevations to assist with planning for future works

Installation of tree protection and a protection scaffold to existing substation

Soft strip and demolition of all existing buildings

Design and install sheet piling to 2nr elevation of site to achieve formation level

Break out of all existing slabs and hardstanding

Removal of underground fuel tanks – dig to locate, sample soil and out a remediation strategy in place prior to removal

Pile probing to a depth of 2m below ground level

Reduce level dig and muck away to achieve levels for future building works

Crush all demolition arisings to a 6f5 grade

Design and lay pile mat to agreed levels

Bray Studios, Windsor

Farmglade / Amazon

Scope of works:

• Brown field / part landfill site
• Site enabling works
• Preparation for driven precast piling
• Gas membrane and ventilation system installed under new stages RC slabs
• Construction of large RC slab for film stages, slabs 4,500m2
• External works & hardstanding
• Site wide drainage and storm water tanks construction

Key Points:

• Working on part landfill site with contamination and gas.
• Rapid delivery programme due to requirements to have the stages built for a new filming production.
• Gas membrane and ventilation system installed due to long term ground gas

Westmead Nursing Home

Wilmott Dixon/Westminster Council

Scope of works:

  • Principle contractor role
    Site enabling works
  • Full Soft Strip to Block and removal of lifts
  • Asbestos Removal
    Supply of capping layer
  • Removal of all obstructions and foundations to the footprint of the building
  • Demolition and site clearance down to Ground slab

Key Points:

  • Working close proximity to other buildings
  • Rapid delivery programme
    Working in a residential area
  • Drug Paraphernalia all over the building